AGEL sets a new milestone in India’s renewable energy (RE) history, adding one of the largest annual greenfield capacities at 5,051 MW. We are now the only company in India to have 19,294 MW operational capacity, strengthening our position as India’s largest RE company. The momentum reflects our unparalleled gigawatt-scale execution capabilities, disciplined project planning and a delivery engine designed to operate at national and global benchmarks.

Execution at Scale

We added 5,051 MW of RE capacity in FY 2025-26, enhancing our total operational capacity to 19,294 MW. The accomplishment marks the fastest and largest capacity addition in India and establishes a new precedent for execution velocity. With this, AGEL becomes the first and only RE company to surpass the landmark of 15,000 MW capacity, primarily through greenfield addition. This reflects both the scale of deployment and our ability to convert capital into operational assets at speed.

The expansion reinforces our leadership in India’s energy transition and positions us among the top 10 global RE independent power producers (IPP). It puts us on a firm trajectory toward the 50 GW target by 2030.

Leading Share of National Capacity Addition

Utility-scale Solar Capacity Addition in FY 2025-26

(MW)

Utility-scale solar capacity addition in FY 2025-26

Wind Capacity Addition in FY 2025-26

(MW)

Wind capacity addition in FY 2025-26

Operational Capacity

(MWac)

Operational capacity by technology

Reaffirming Leadership

19,294 MW

Operational renewable portfolio capacity (India’s largest, among the top 10 globally and the only RE company in India to reach this milestone)

13,515 MW

Solar power plants operationalised

2,563 MW

Wind power plants operationalised

3,216 MW

Hybrid

1,376 MWh

BESS

Highlights of Our Milestone

  • ~26.67 million tonnes annual carbon emissions avoided (equivalent to carbon sequestered by ~1,270 million trees or ~5.8 million cars off the road)
  • ~6.4 million households can be powered by our operations capacity

Project Development Excellence

Our expansion is driven by a robust greenfield development engine, supported by advanced resource planning, engineering, and supply chain management. Project management, execution assurance, and on-ground coordination by Adani Infra India Ltd further ensure disciplined and timely execution across diverse geographies and technologies.

Scaling at Speed

First10,000MW

delivered in 8 years

Next9,294MW

delivered in 2 years; 5.1 GW in FY 2025-26 alone

Next30,000MW

Planned over the next 4 years